How govt is fast-tracking 4 huge hydropower tasks in Kashmir after Indus Waters Treaty suspension
&w=1200&resize=1200,0&ssl=1)
India has superior the beginning date of 4 under-construction hydropower tasks within the Kashmir area after the suspension of the 1960 Indus Waters Treaty with Pakistan. We check out progress to this point on every mission
learn extra
India has superior the beginning date of 4 under-construction hydropower tasks within the Kashmir area after the suspension of the 1960 Indus Waters Treaty with Pakistan, based on a Reuters report, citing authorities doc and an trade supply.
The up to date schedule for the tasks, whose development Pakistan usually opposes as a result of it fears it might result in much less water downstream, is one other signal of how India is attempting to reap the benefits of its unilateral suspension of the Indus Waters Treaty of 1960 following a lethal assault in Pahalgam final month, which claimed 26 lives, added the report.
India’s choice to droop the treaty and expedite these tasks indicators a major coverage shift geared toward asserting larger management over its water sources in response to cross-border terrorism.
Earlier at this time, Prime Minister Narendra Modi additionally reaffirmed authorities’s stance, saying that the choice to place a freeze on the Indus Water Treaty is not going to be reversed and that India’s water will circulate for India’s profit.
Talking at an ABP Community occasion on Tuesday night, PM Modi stated, “Today, there may be lots of dialogue within the media about water… Earlier, even the water that was India’s proper was flowing in a foreign country. Now, India’s water will circulate for India’s profit, it will likely be conserved for India’s profit, and it will likely be used for India’s progress”.
In response to Reuters, citing the doc, Modi authorities has requested authorities to clear hurdles to speedy development of 4 hydro tasks with a mixed capability of three,014 megawatts.
The 4 tasks are: Pakal Dul (1,000 MW), Kiru (624 MW), Kwar (540 MW) and Kirthai Stage-1 (930 MW). All of them are on the Chenab River, whose waters are primarily meant for Pakistan however India is allowed to construct run-of-water hydro tasks with none vital storage.
We check out progress to this point on every mission as India accelerates strategic hydropower growth following treaty withdrawal:
1. Pakal Dul HE Mission (1,000 MW)
-
Options the best concrete-faced rock-fill dam in India at 167m; 72m of dam peak already constructed with 24.78 lakh cubic meters crammed
-
Head Race Tunnel excavation underway at a quick tempo — essential to mission completion
-
Spiral casing for Unit-1 and Unit-2 accomplished in February 2024
-
Authorities has accepted establishing transmission traces to expedite energy evacuation
-
Consents for energy provide acquired from Haryana, Maharashtra, Karnataka
2. Kiru HE Mission (624 MW)
-
Dam concreting works are important; 3.5 lakh cubic meters accomplished out of a complete 13.95 lakh cubic meters
-
Mission is progressing in keeping with scheduled timelines
-
Energy Buy Settlement (PPA) for 543 MW signed with Gujarat Urja Vikas Nigam Ltd (GUVNL)
-
Consents for energy buy acquired from Chhattisgarh, Uttar Pradesh, and Karnataka
3. Kwar HE Mission (540 MW)
-
Achieved main milestone in January 2024 with diversion of River Chenab — paving the way in which for dam development
-
Foremost dam works now actively underway
-
PPAs signed with CSPDCL and GUVNL
-
Energy buy consents acquired from Haryana, Maharashtra, and Karnataka
4. Kirthai Stage-1 (930 MW)
-
A run-of-river mission situated 25 km upstream of Kiru in Kishtwar district, J&Ok
-
Designed to generate 3,329.52 million items yearly (90% reliable 12 months)
-
Contains 121m excessive concrete gravity dam
-
Mission launch cleared after India suspended IWT — earlier requirement for treaty clearance now not relevant
With inputs from businesses